Positioning Your Facility Project for Success
A proactive approach to project scheduling and risk management can minimize pitfalls.
November 2010
Even when projects are well-designed, if they fail to meet budget and scheduling requirements, it is often because project managers struggle with the dynamics of scheduling and risk management. While studies have not precisely traced the percentage of projects that fail because of an encounter with unforeseen risks, it is probable that any project that runs into major unanticipated difficulties will finish late and over budget.
Meanwhile, researchers have looked at failures stemming specifically from scheduling problems. They have found that 39 percent of failed projects can be attributed to project managers' losing control of schedules. But losing control of a schedule is only part of the problem. The biggest contributor to failure is an unrealistic schedule, which can be tied to many factors, including poor scope definition and risk planning, as well as lack of definition of a "complete" project. Therefore, to enable projects to succeed, project managers must be proactive and anticipate and resolve the problems that undue risks and the resultant uncontrolled schedules can cause.
Risk and Opportunity
As the economy was falling into decline two years ago, the estimation process began on a brownfield project. A new factory was slated to be constructed on an abandoned factory site. The engineers identified a risk related to the availability of construction resources: building material manufacturers, fearing a declining market caused by the coming recession, would probably cut back on production to avoid building up inventories. In these circumstances, construction materials would be difficult to acquire in a timely manner.
The engineering team and project managers mitigated that problem by speeding up the development of the construction documents. Then, they turned the scarcity risk into an opportunity. Assuming that building material manufacturers would likely make and sell products at lower prices whenever possible, in order to maintain revenues and avoid laying off experienced workers during the downturn, the project managers pounced on the cost-saving opportunity and ended up shaving 25 percent off the original building materials estimate.
Had the risk not been identified and dealt with ahead of time, subcontractors would have had to delay the project waiting for materials, thereby delaying the schedule; alternately, they would have had to pay rush fees to ensure on-time delivery, negatively impacting the budget.
Seek Out Risks
In order to manage risks, they must first be identified. An effective, risk identification methodology encompasses the following five steps:
1. Gather the most knowledgeable people in each project discipline - procurement, operations, management, engineering, supply chain, and so on - and form a risk management team. The team's attention must be focused on the need to manage risks, and they must discuss the level of risk assessment appropriate to the project.
2. The project manager then asks each member of the risk management team to list four to six risks that he/she foresees developing during the project - along with any opportunities embedded in those risks. Once everyone has submitted a list, the team meets, eliminates any duplicate ideas, and brainstorms for additional risks to add to the list. The risks are evaluated in a qualitative sense for likelihood of occurrence and severity of impact.
3. Next the team assigns the practical risks to team members, who will develop countermeasures. It would be a waste of time to prepare for any risks that have little likelihood of occurring - beyond taking the normal life-safety precautions followed at every project site. But each of the practical risks should receive attention.
For example, development of a brownfield site involves utilizing abandoned site infrastructure that has fallen into disrepair. Site investigation can reveal environmental hazards that need to be addressed quickly. When these types of risks are identified up front, mitigation plans can be created that allow the project to be successful.
4. The team reviews all of the work needed, commenting on and refining the countermeasures suggested for each risk.
5. Finally the team sets a schedule to review and evaluate the risks, as well as the progress of the countermeasures. Such a schedule should call for weekly, monthly, and quarterly meetings as the project progresses.
The weekly meeting includes informal progress reviews and group comments designed to maintain focus on the risk. The monthly and quarterly meetings are more formal and designed to check off risks as having been avoided or not. If not, the team reviews the mitigation plan and ensures that it is on track. If it isn't, additional countermeasures are developed and implemented.
In addition, an evaluation of risk status should be performed to determine whether the risks have elevated up or down, as well as whether any new risks have surfaced. Of course, the regular meetings must also deal with risks that arise during the course of a project.
Project Announcements
Apex Plastics Opens Expanded Production Plant In Brookfield, Missouri
09/22/2014
Japan-Based Bridgestone Rubber-BSA Opens Biorubber Process Research Center In Mesa, Arizona
09/22/2014
SpencerARL Expands Its Plattsburgh, New York, Manufacturing Facility
09/22/2014
Hill International, Inc. Relocates Corporate Headquarters To Philadelphia, Pennsylvania
09/22/2014
Prysmian Group Plans $8.2 Million Expansion At Abbeville County, South Carolina, Manufacturing Center
09/22/2014
Japan-Based Kowa Kentucky Plans $8.3 Million Manufacturing Facility In Corbin, Kentucky
09/22/2014
Most Read
-
Top States for Doing Business in 2024: A Continued Legacy of Excellence
Q3 2024
-
The Role of Rail in Industrial Development
Q4 2024
-
Hydrogen Industry in Canada: A Global Leader in the Clean Energy Revolution
Q3 2024
-
Exploring the Dynamic Landscape of Industrial Packaging Solutions
Q3 2024
-
Which AI Tools Work for Job Recruiters?
Q3 2024
-
Cold Storage: The Next Big Thing in Industrial Real Estate
Q3 2024
-
Permitted Power Capacity Foreshadows Health of Regional Economies
Q3 2024